Impact of Level on Performance

SEI
Level
Quality
Defects /KSLOC
Productivity
SLOC /Hour
Cost
$ Millions
Cost
$/SLOC
Development
Time
19.0+1.0$33 M$6640 Months
23.03.0$15 M$30 32 Months
31.05.0$ 7 M$1425 Months
40.38.0$ 3 M$619 Months
50.112.0$ 1 M$216 Months

SEI
Level

Duration
(Months)
Effort
(Man-Months)
Faults Detected
during Development
Faults DeliveredTotal Cost
129.5593.5134861$5,440,000
218.5143.0328121,311,000
315.279.51827728,000
412.542.8975392,000
59.016.0371146,000

(From Schach (1996) Classical and Object Oriented Software Engineering. p. 74)
(Model for a 200K data processing application)


Project performance compared to estimated performance. This example demonstrates different projects in the US Air Force. From Steve McConnell The Business of Software Improvement. IEEE SOFTWARE Vol. 19, No. 4; JULY/AUGUST 2002, pp. 5-7 Steve McConnell